Trusted experience of over 30 years
01773 424150
info@trisonltd.co.uk
The installer should complete this section and include details of the commissioning engineer.
1.1 Installation address details
Dwelling name/number
Street
Town
County
Postcode
1.2 System details
System classification*
Enter ‘natural ventilation’, ‘mechanical extract ventilation’ or ‘as defined by Approved Document F’.
Manufacturer
Model numbers
Serial number (where available)
Location of fan units
1.
2.
3.
4.
5.
6.
7.
1.3 Installation engineer's details
Engineer's name
Company
Address line 1
Address line 2
Telephone number
1.4 Commissioning engineer’s details (if different to 1.3)
Email address
*NOTE: If a system has been installed that is not defined in Approved Document F, further installation checks and commissioning procedures may be required. Seek guidance from the manufacturer for such systems.
The installer should complete this section before commissioning is carried out.
2a.1 Installation checklist – general (all systems)
Tick as appropriate
Has the system been installed in accordance with the manufacturer’s requirements?
YesNo
Have paragraphs 1.12 to 1.83(1) been followed (if relevant)?
If there are any deviations from paragraphs 1.12 to 1.83, give details here
Description of installed controls (e.g. timer, central control, humidistat, occupancy sensor, thermal bypass, if applicable, etc.)
Location of manual/ override controls
2a.2 Installation engineer’s declaration
Engineer’s signature
Registration number (if applicable)
Date of inspection
NOTE: 1. All references to tables and paragraphs are to Approved Document F, Volume 1: Dwellings.
The commissioning engineer should complete this section before completing Part 3.
2b.1 Visual inspections – general (all systems)
What is the total installed equivalent area of background ventilators in the dwelling?
mm2
What is the total floor area of the dwelling?
m2
Does the total installed equivalent ventilator area meet the standards detailed in Table 1.7 or paragraph 1.57(1), as appropriate?
Have the correct number and location of extract fans/terminals been installed to satisfy the standards in Table 1.1 or Table 1.2, as appropriate?
Is the installation complete, with no obvious defects?
Do all internal doors have enough undercut to allow air transfer between rooms as detailed in paragraph 1.25 (i.e. 10mm above the floor finish or 20mm above the floor surface)?
Has all protection/packaging been removed (including from background ventilators), so that the system is fully functional?
Are systems clean internally and externally?
Has the entire system been installed to allow access for routine maintenance and to repair/replace components?
2b.2 Visual inspections – general (continuous mechanical extract ventilation and mechanical ventilation with heat recovery systems only)
Have appropriate air terminal devices been installed to allow system balance?
Have the heat recovery unit and all ductwork been effectively insulated and sealed for all heated and unheated spaces?
Is the condensate connection complete and does the condensate drain to an appropriate location (mechanical ventilation with heat recovery only)?
Are filters installed?
For ducted systems, has the ductwork been installed so that air resistance and leakage is kept to a minimum?
2b.3 Other inspections – general (all systems)
At initial start-up, was there any abnormal sound or vibration, or unusual smell?
During continuous operation, was there any excessive noise?
The commissioning engineer should complete this section after completing Part 2b.
3.1 Commissioning equipment
Schedule of air flow measurement equipment used (model and serial number)
Date of last UKAS calibration
3.2 Air flow measurements – intermittent extract fans only
Fan reference (from section 1.2 above)
Measured extract rate (l/s)
Design extract rate (l/s) Refer to Table 1.1(1)
Extract fan 1
Extract fan 2
Extract fan 3
Extract fan 4
For cooker hoods, only the highest setting needs to be recorded.
3.3 Air flow measurements (extract) – continuous mechanical extract ventilation and mechanical ventilation with heat recovery only
Room reference (location of terminals)
Measured air flow – high rate (l/s)
Design air flow – high rate (l/s) Refer to Table 1.2
Measured air flow – continuous rate (l/s)
Design air flow – continuous rate (l/s) Refer to Table 1.3
Kitchen
Bathroom
En suite
Utility
WC
Other
3.4 Air flow measurements (supply) – mechanical ventilation with heat recovery only
Living room 1
Living room 2
Dining room
Bedroom 1
Bedroom 2
Bedroom 3
Bedroom 4
Bedroom 5
Study
3.5 Commissioning engineer’s declaration
Date of commissioning